By Rabiu Sanusi
Kano state government has concluded arrangement to complete the abandoned 5 kilometers rural road projects across the 44 local government areas of the state.
Governor Abba Kabir Yusuf gave the assurance after a reconciliation meeting with contractors handing the capital projects at Government House.
The multi-million naira 5 kilometers rural urban road projects which were awarded by former Governor, Dr. Rabiu Musa Kwankwaso during his administration had suffered total neglect by immediate past administration of Abdullahi Umar Ganduje.
Governor Abba also commended the contractors for their timely response, assured his administration’s resolve to sustain Dr. Kwankwaso’s rational behind road infrastructure.
Hotpen reports that critical of mutual agreements reached after the meeting includes immediate mobilization of the handlers back to sites in the next one week to complete the project.
Other resolutions concluded between the two parties are, the urgent directive issued to state Ministry of Land and Physical Planning to sort out issues of pending compensation problem.
It was resolved that contractors would meet with their respective banks to access 30 percent advance payment released to the contracts but failed to access it.
It was further resolved a result of recorded escalation in the prices of construction materials, that government has accepted to review the cost of the remaining items of works based moderate upward reviewed rates.
It was also agreed that goverment would fashioned out a planned strategic payments to contracts on monthly basis such that no payment is stagnated.
The resolution had that contractors that accepted the new offer should mobilize to their respective sites within one week otherwise forfeit the opportunity.